Weib Feasibility Study and Detail Design of Irrigation Project
On Going
Weib Feasibility Study and Detail Design of Irrigation Project
Region
Oromia and Somali National Regional State
Zone | Woreda
Oromia - Bale Zone | Dawe Serari
Somali - Afdare | Chereti
Equipped Areas
4,890.49 Hectares
Type of Headwork
Diversion Weir
Date Contracted
June, 2021 GCE
Date Completed - Expected
September, 2022 GCE
Project Cost
20,289,966.98 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Lower Genale Feasibility Study and Detail Design of Irrigation Project
On Going
Lower Genale Feasibility Study and Detail Design of Irrigation Project
Region
Oromia and Somali National Regional State
Zone | Woreda
Oromia - Guji Zone | Liben Woreda - | Bale Zone | Meda - Welabu Woreda
Somali - Liben Zone | Kersa dula and Dekasuftu Woreda
Equipped Areas
17,000 Hectares
Type of Headwork
Diversion Weir
Date Contracted
March, 2021 GCE
Date Completed - Expected
November, 2022 GCE
Project Cost
51,133,046.04 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Lower Genale Feasibility Study and Detail Design of Irrigation Project (Lot-II)
On Going
Lower Genale Feasibility Study and Detail Design of Irrigation Project (Lot-II)
Region
Somali National Regional State
Zone | Woreda
Liben and Afder | Dolo-ado, Bekolmayu and Dolo-bay
Equipped Areas
38,000 Hectares
Type of Headwork
Diversion Storage and Lifting
Date Contracted
June, 2021 GCE
Date Completed - Expected
November, 2022 GCE
Project Cost
96,082,127.93 Ethiopian Birr
Irrigation System
Furrow Irrigation System (Gravity System)
Gillo Feasibility Study and Detail Design of Irrigation Project